Work in progress: Myzeqe Agricultural Ring, Lot II
Works are in progress for the agricultural development of the area and the country.
Currently works are focused on the construction of sidewalks, where 1.1 km is completed. Meanwhile in Qerret works are proceeding on the construction of the borders of the sidewalks.
The ballast layer (1.9 km) is completed and is ready for stabilizer.
Lot II (Qerret-Kadiaj 2.7 km) is expected to be completed within this year, and after that works will continue with the Kadiaj-Saver segment.
Meanwhile, the whole area has about 6700 ha of cultivated land, 189 ha of greenhouses and 93 ha trees. The Agricultural Ring of Myzeqe will provide a faster access to market and at a lowest cost.