Tirana- Works for cementing the water storages in Dvoran (200m3) and Kamenica have been completed.
41% of works have been completed with high quality materials.
In this water supply have been laid about 8.5 km of pipelines(85% of the total) and 18 km of distribution network (about 82%).

The cement works have been completed. Meanwhile, stone filling and isolation works are proceeding in Saliaj and Zgerfella. Cement works in the septic tank is in progress.
Installation with the supply network has begun.
The intervention is implemented by the Albanian Development Fund and aims to supply the families of the area with and quality potable water, in line with EU guidelines.