TIRANA- Reconstruction works on the asphalt sub-base of ‘Tre Urat-Cerme Sektor’ segment, in the Agricultural Ring Road of Divjaka have been completed, and very soon will start the placement of horizontal signage.

Project work started on March 2015 and was completed in July 2016.

The entire ring road passes through a marsh area and slippages cracking were avoided since the design stage.

Repairs were carried out after some cracks in various sections along ‘Tre Urat-Cerme Sektor’ segment. The repair surface was from 1 to 20 square meters. The problem has emerged during 2017 and is kept under constant control by a working group (construction engineers, geology engineers) of the Albanian Development Fund. After the observation of the problematic points, geologists determined the final repairs, which were carried out two months ago.

 

 

In order to ensure sustainability and uniformity with the rest of the road were paved 6km road.

Divjaka Agricultural Ring Road project is implemented by the Albanian Development Fund on the behalf of the Albanian government. The object is in guarantee phase, which means that all repair costs are covered by contracted firms.