Tiranë-Works for the reconstruction of the road Kuqan-Bujqës are proceeding at a high pace.
About 650 ml of binder layer have been completed in the segment Bujqes-Jagodine as well as the tiles of the ballast layers in the Kuqan-Bujqes segment (1.3km) . Asphalt will be laid in the coming days
Meanwhile, in the segment Murriqan-Thane are proceeding other constructional works.

This axis connects the richest agricultural and livestock areas in the country, where the improvement of the infrastructure will provide faster exit to the markets, directly affecting the increase of production and special products that these villages offer.