NOTIFICATION OF CONTRACT AWARD DECISION
Employer: Albanian Development Fund
Project: Community Works IV: Development of the Albanian Alps and Coastal Areas
Assignment Title“Supervision Services for Civil Works in Ulza’s road”.
Country: Albania
Loan No.: ALB – LD 1853
RFB No:CWPIV/CS/RP/2017/17
Issued on: October 31, 2017
The duration and summary scope of the contract: The overall envisaged period of implementation of the project is 8 months. One of the project objectives is the urban requalification of the territory in Mat Municipality. The Consultant will supervise civil works that will be carried out in the frame of this project, including monitoring, inspection and reporting activities.
I. The Bidders who submitted a Bid:
1) “A&E Engineering” shpk
2) JV “Erald – G” shpk & “THC” shpk
II. The bid prices as read out at bid opening:
1) “A&E Engineering” shpk – 1,890,000 ALL, Exclusive of VAT
2) JV “Erald – G” shpk & “THC” shpk – 1,850,000 ALL, Exclusive of VAT
III. The Bidders and evaluated prices of each Bid that was evaluated:
1) “A&E Engineering” shpk – 1,890,000 ALL, Exclusive of VAT
2) JV “Erald – G” shpk & “THC” shpk – 1,850,000 ALL, Exclusive of VAT
IV. The bidders whose bids were rejected and the reasons for their rejection: There were not rejected bidders.
V. The winning Bidder, and the price it offered after completing contract price negotiations: JV “Erald – G” shpk & “THC” shpk – 1,850,000 ALL, Exclusive of VAT.
VI. The standstill period is 10 days.
VII. The complaint during the standstill period may by submitted at:
Albanian Development Fund
Street Address: Rr. Sami Frasheri, No. 10
Floor/Room number: Ground Floor, Protocol Office
City: Tirana
Country: Albania