CONTRACT AWARD NOTICE

 

Implementing Agency: Albanian Development Fund

Country: Albania

Project: Regional and Local Roads Connectivity Project (RLRCP) (Project No. P163239)

Loan No.: 8850-AL

Assignment Title: “Supervision services for roads reconstruction (approx. 45 km)”

Reference No: RLRCP/1/1.6/2018

Issued on: April 14, 2020

 

I.  The selection method used: Consultants Quality and Cost-based Selection (QCBS) method set out in the Procurement Regulations.

II.  The Consultants who submitted proposals, and the proposal prices as read out and as evaluated:

No
Name of Consultant
Proposal Price as read out

Exclusive of taxes

Proposal Price as evaluated

Exclusive of taxes

1.
“Dolsar Engineering Inc. Co”
813,700 UD$
813,700 UD$
2.
“Eptisa Servicios de Ingenieria” sl
680,020 US$
680,020 US$
3.
JV “Institut IGH” d.d. & “Taulant” shpk
1,439,550 Euro
1,439,550 Euro
4.
JV “Pan Arab Consulting Engineers” ltd (Pace-Kuwait) & “Erald-G” shpk
791,240 US$
791,240 US$
5.
JV “SAJDI-Consulting Engineering Center” & “IPSA Institute” doo
1,485,600 US$
1,485,600 US$
6.
JV “Tecnic Consultin Engineers” spa & “Sipas” spa & “Infra-Plan” shpk
944,264 Euro
944,264 Euro
7.
“Roughton International Limited” ltd
968,800 Euro
968,800 Euro
8.
“SPEA Engineering” spa
996,050 Euro
996,050 Euro

III.  The Consultants whose Proposals were rejected and the reasons therefor: “SPEA Engineering” spa – Failure and termination of the contract negotiations.

IV.  The Consultant submitting the successful proposal: “Eptisa Servicios de Ingenieria” sl. : Emilio Munoz, 35-37, 28037, Madrid Spain.

V.  The Contract price: 816,024 US$ (eight hundred sixteen thousand and twenty-four), VAT included.

VI.  The duration and summary scope of the contract: The duration of the project is foreseen for 18 (eighteen) months and a further 24 months of Defects Notification Period.

Main objective of the service consists in carrying out the supervision of three or more adjacent road works contracts, based on the available designs and bidding documents prepared by a separate consultant. The consultant’s team will provide for both overall management and also supervision of the works contracts.

VII.  Successful Consultant’s Beneficial Ownership Disclosure Form